Forthcoming Major Roadworks in Wandsworth


Traffic delays likely in the area due to road and lane closures

Forthcoming Major Roadworks in Wandsworth

A3 West Hill, Wandsworth
26 February — 03 March
Delays likely - Traffic control (two-way signals)
Works description : NEW GAS SERVICE TO 63A AND 63C EXACAVATING IN THE N/S C/W USING 2 WAY LIGHTS TO MAINTAIN C/W EXCAVATING IN N/S F/W MAINTAINING 1M FOR PEDS
Responsibility for works: SGN
Current status: Planned work about to start
Works reference:  XW047W117019131-06045

B229 Bolingbroke Grove, Battersea
25 February — 25 February
Delays likely - Traffic control (multi-way signals)
Works description : SEW DESCALE EMERGENCY/REACTIVE
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU026003345HVWK--000005

B229 Burntwood Lane, Tooting
25 February — 27 February
Delays likely - Traffic control (two-way signals)
Works description : Install 1m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500292505701

Louvaine Road, Battersea
26 February — 28 February
Delays likely - Road closure
Works description : Install 4m of 1 way poly duct in Footway,Install 7m of 1 way poly duct in Carriageway,Provide 1 core drill(s) into jointbox or building
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500287126701

A3205 York Road, Wandsworth
24 February — 26 February
Delays likely - Lane closure
Works description : sewer surveys- tideway
Responsibility for works: THAMES TIDEWAY TUNNEL LTD
Current status: Planned work about to start
Works reference:  ZE4103159-YR-60

B229 Bolingbroke Grove, Battersea
25 February — 25 February
Delays likely - Traffic control (multi-way signals)
Works description : SEW DESCALE EMERGENCY/REACTIVE
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU026003345HVWK--000005

B229 Burntwood Lane, Tooting
25 February — 27 February
Delays likely - Traffic control (two-way signals)
Works description : Install 1m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500292505701

A214 Woodwell Street, Wandsworth
27 January — 01 March
Delays likely - Lane closure
Works description : WBS SC.2769.254.001 s278 works - Woodwell St footway works from 27/01/20 - 14/02/20 - lane closure & Woodwell St on to Huguenot Pl footpath / corner works from 17/02/20 - 01/03/20 - lane closure. TM plan: 2. Woodwell Street 27.01.19-01.03.20 TMAN
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG429424795

A217 Garratt Lane, Tooting
26 February — 28 February
Delays likely - Contra-flow
Works description : Install 8m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500288227001

Aboyne Road, Tooting
10 February — 09 March
Delays likely - Road closure
Works description : Excavate on all side connection mains within Aboyne Road between Strathdon Drive & Barnfield Close under hase two road closure. Foam off, tranfer onto new 250 PE main which has been inserted inside existing 12" Iron main from Stranthon Drive to junc opp Barnfield Close. Old main thrown dead, new PE Main gassed up, tested. Backfill and reinstate, road closure lifted.
Responsibility for works: SGN
Current status: Planned work about to start
Works reference:  XW053W117008418-00006

A3205 York Road, Wandsworth
08 February — 21 March
Delays likely - Traffic control (multi-way signals)
Works description : Set up site and mark up for open cut. Open cut and lay approx. 23 meters of 180mm PE L/P. Tie onto existing 90mmPE main located. Backfill & reinstate leaving connection hole open for commissioning. Set up site and mark up for open cut. Open cut and lay approx. 22 meters of 180mm PE L/P. Tie onto new 180mmPE main. Backfill & reinstate leaving connection hole open for commissioning .
Responsibility for works: SGN
Current status: Advanced planning
Works reference:  XW053W116850254-06622

A3 Huguenot Place, Wandsworth
06 January — 01 March
Delays likely - Lane closure
Works description : WBS SC.2769.254.001 s278 works - Woodwell St footway works from 27/01/20 - 14/02/20 - lane closure & Woodwell St on to Huguenot Pl footpath / corner works from 17/02/20 - 01/03/20 - lane closure. TM plan: 2. Woodwell Street 27.01.19-01.03.20 TMAN
Responsibility for works: Transport for London
Current status: Advanced planning
Works reference:  YG429424815

Trinity Road
Until May 2021
Some delays likely - lane closure
Works location: A214 Trinity Road
Works description:Vehicle holding area for Thames Tideway construction
Responsibility for works: TfL
Current status: Works started

Water Leaks and Gas Escapes

Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

For instance via their telephone number, or Mr Don Ogunyemi on Tel No 020 8871 6712, Fax 020 8871 3174, E-mail dogunyemi@wandsworth.gov.uk.

February 26, 2020