Forthcoming Major Roadworks in Wandsworth


Traffic delays likely in the area due to road and lane closures

Forthcoming Major Roadworks in Wandsworth

A3 North Side Wandsworth Common, Wandsworth
11 March — 12 March
Delays likely - Traffic control (two-way signals)
Works description : EXCAVATE IN C/W TO UNCOVER AND OVERHAUL LEAKING CRITICAL TRUNK MAIN VALVE BACK FILL AND REINSTATE
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU277HCV6972212-01

A3 West Hill, Wandsworth
09 March — 10 March
Delays likely - Traffic control (multi-way signals)
Works description : 10/062 tel0250087 - slot cut c/w sensor loops to repair traffic signals SD2 plus feed to existing chamber (f/w 2m new duct and underkerb) 22:00-05.00, westbound c/w lane 1 and f/w to chamber (ped access maintained) Temp signals will be manually controlled. Bus stop: 26144 suspended
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG516S000000005464

A214 Trinity Road, Wandsworth
08 March — 20 March
Delays likely - Road closure
Works description : Carrigeway Resurfacing, line marking, iron works; Road closure
Responsibility for works: Transport for London
Current status: Advanced planning
Works reference:  YG423419442

A218 Durnsford Road, Wimbledon Park
12 March — 12 March
Delays likely - Traffic control (Stop/Go boards)
Works description : 22/135 TEL0259398 - RECUT OF MAGNETOMETER SD1, 20:00 - 05:00, LANE 1 - NORTHBOUND. ILLUMINUATED STOP/GO BOARDS TO BE USED
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG516S000000005734

A3036 St Johns Hill, Battersea
11 March — 13 March
Delays likely - Traffic control (two-way signals)
Works description : Remedial works to correct defect, replace 30 damaged Chinese granite, replace bricks used instead of granite, replace cracked tactiles
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500283113501

B229 Burntwood Lane, Tooting
10 March — 12 March
Delays likely - Traffic control (two-way signals)
Works description : Install 1m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC006TI001LC500292505702

Plough Road, Battersea
07 March — 18 April
Delays likely - Lane closure
Works description : Set up site and mark up for open cut. Open cut and lay approx. 45 meters of 180mm PE L/P. Tie onto new 180mmPE main. Backfill & reinstate leaving connection hole open for commissioning. Set up site and mark up for open cut. Open cut and lay approx 80 meters of 180mm PE L/P. Tie onto existing 180mmPE main at Junction of Holgate Avenue and new 180mmPE. Commission new 180mmPE main. Backfill & reinstatement to commence.
Responsibility for works: SGN
Current status: Advanced planning
Works reference:  XW053W116850338-03882

A217 Garratt Lane, Tooting
05 March — 18 March
Delays likely - Contra-flow
Works description : Permit for trial holes only.
Responsibility for works: SGN
Current status: Planned work about to start
Works reference:  XW053W117041172-01883

A3205 York Road, Wandsworth
08 February — 21 March
Delays likely - Traffic control (multi-way signals)
Works description : Set up site and mark up for open cut. Open cut and lay approx. 23 meters of 180mm PE L/P. Tie onto existing 90mmPE main located. Backfill & reinstate leaving connection hole open for commissioning. Set up site and mark up for open cut. Open cut and lay approx. 22 meters of 180mm PE L/P. Tie onto new 180mmPE main. Backfill & reinstate leaving connection hole open for commissioning .
Responsibility for works: SGN
Current status: Advanced planning
Works reference:  XW053W116850254-06622

Trinity Road
Until May 2021
Some delays likely - lane closure
Works location: A214 Trinity Road
Works description:Vehicle holding area for Thames Tideway construction
Responsibility for works: TfL
Current status: Works started

Water Leaks and Gas Escapes

Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

For instance via their telephone number, or Mr Don Ogunyemi on Tel No 020 8871 6712, Fax 020 8871 3174, E-mail dogunyemi@wandsworth.gov.uk.